Buttimer Engineering has successfully completed the design and build of several large-scale grain transfer and storage facilities for us across Poland. We were impressed by their professional approach to the job and high-quality solution provided, and would have no hesitation recommending them.
Coolkeeragh Power Station
About The Project
Erection of boiler exhaust stack at Coolkeeragh CCGT power station, Co. Derry (400 MW).
The free standing stacks were 6m in diameter, 70m in height and weighing 150 Tonnes
Design, manufacture (including insulation) and erection of Stack for Coolkeeragh Power Station.
Detailed design of all aspects including boiler exhaust stack.
Stack dimensions: Diameter 6m, Height 70m and Weight 150 Tonnes.
Exhaust system reduces noise pollution.
Exhaust system included diffuser and diverter.
Client Name: Standard Fasel
Location: Derry, Northern Ireland